Sizing tasks to the gap available
Gaps between events vary from overnight to several weeks, and the right work is different in each. An overnight gap suits amenities, corridors and dock aprons. A few days allows kitchen deep cleaning, store clearing and floor treatment in defined areas. An extended break allows high-level work, plant areas and anything requiring access equipment.
The plan should therefore hold three task lists rather than one schedule. When a gap appears, the appropriate list is used. That structure means a two-day window is not spent on work that could have been done overnight, and it means a rare extended break is recognised as the opportunity it is rather than treated as a quiet period. Recording which list applies to which gap length, in the plan itself, is what allows a window to be used without a planning conversation first.